Professional Scrum Master I (PSM I) — Question 61
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what `Done` means. (Choose two.)
Answer options
- A. All work the Development Team is willing to do.
- B. Ready for integration.
- C. No work left from the definition of ג€Doneג€.
- D. Whatever the Product Owner defines as quality.
- E. Ready to be released to end users.
Correct answer: C, E
Explanation
'Done' signifies that there are no outstanding tasks according to the definition of 'Done' (C), and that the Increment is completed to the extent that it can be released to end users (E). Options A, B, and D do not accurately capture the full meaning of 'Done' as they either imply incomplete work or subjective quality definitions.