Who creates a Product Backlog Item's estimate?
Answer options
- A. The Development Team after clarifying requirements with the Product Owner.
- B. The Product Owner with input from the Development Team.
- C. The most senior people in the organization, including architects and subject matter experts.
- D. The Scrum Master.
- E. The Development Team, alone.
Correct answer: A
Explanation
The correct answer is A because it is the Development Team that is responsible for estimating the effort required for Product Backlog Items after discussing and clarifying requirements with the Product Owner. Options B and E suggest involvement from the Product Owner or the Development Team alone, which does not reflect the collaborative nature of the estimation process. Options C and D are incorrect as they do not involve the Development Team in the estimation process.