Professional Scrum Master I (PSM I) — Question 59

What is the timebox for the Sprint Planning event?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the timebox for Sprint Planning is set to 8 hours for a one-month Sprint. Option A is incorrect because 4 hours is too short for a monthly Sprint. Options C and D are not specific enough to define a timebox and therefore do not meet the requirement.