Professional Scrum Master I (PSM I) — Question 57
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Answer options
- A. Run the Daily Scrum.
- B. Prioritize the Development Team's work on the Sprint Backlog.
- C. Update the Sprint burndown chart.
- D. Answer questions from the Development Team about items in the current Sprint.
- E. Work with the stakeholders.
Correct answer: D, E
Explanation
The correct answers are D and E because the Product Owner is responsible for clarifying any questions the Development Team may have about the Sprint items and engaging with stakeholders to gather feedback. Options A, B, and C are responsibilities of the Scrum Master or the Development Team, not the Product Owner.