Professional Scrum Master I (PSM I) — Question 23

How much of the Sprint Backlog must be defined during the Sprint Planning event?

Answer options

Correct answer: C

Explanation

The correct answer is C because it emphasizes the need for the Development Team to have enough information to make an informed forecast for the Sprint's initial days. Option A is misleading as it focuses on the Scrum Master's confidence rather than the Development Team's planning. Option B is incorrect since not the entire Sprint Backlog needs to be defined upfront. Option D is too limited, as it only addresses design and architectural aspects without considering task estimation.