Professional Scrum Master I (PSM I) — Question 23
How much of the Sprint Backlog must be defined during the Sprint Planning event?
Answer options
- A. Just enough tasks for the Scrum Master to be confident in the Development Team's understanding of the Sprint.
- B. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
- C. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
- D. Just enough to understand design and architectural implications.
Correct answer: C
Explanation
The correct answer is C because it emphasizes the need for the Development Team to have enough information to make an informed forecast for the Sprint's initial days. Option A is misleading as it focuses on the Scrum Master's confidence rather than the Development Team's planning. Option B is incorrect since not the entire Sprint Backlog needs to be defined upfront. Option D is too limited, as it only addresses design and architectural aspects without considering task estimation.