Professional Scrum Master I (PSM I) — Question 22

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Answer options

Correct answer: D

Explanation

The correct answer, D, indicates that the Sprint Backlog represents the Scrum Team's plan for the Sprint, outlining how they will achieve the Sprint Goal. Options A, B, C, and E do not accurately reflect the essence of the Sprint Backlog, as it is not required to be a complete list, have designated owners for each item, have tasks estimated in hours, or be ordered by the Product Owner.