Professional Scrum Master I (PSM I) — Question 21

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Answer options

Correct answer: A, B, F

Explanation

Choosing A, B, and F highlights the importance of regular inspection and adaptation in Scrum. If the Daily Scrum is less frequent, opportunities to adjust the Sprint Backlog are missed (A), impediments are not resolved quickly (B), and the Sprint plan may not reflect the current state of work (F). Options C, D, and E, while relevant, do not directly address the core concerns of reducing the frequency of the Daily Scrum.