Professional Scrum Master I (PSM I) — Question 20

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Answer options

Correct answer: B, C

Explanation

The correct answers, B and C, highlight the importance of communication and engagement in the project. If the Product Owner does not keep stakeholders informed, they may lose trust and oversight, leading to unmet expectations. Additionally, if stakeholders do not actively participate in Sprint Reviews, they miss opportunities to provide feedback, which can result in misaligned project goals.