How should a Development Team deal with non-functional requirements?
Answer options
- A. Ensure every Increment meets them.
- B. Make sure the release department understands these requirements, but it is not the Development Team's responsibility.
- C. Handle them during the Integration Sprint preceding the Release Sprint.
- D. Assign them to the lead developers on the team.
Correct answer: A
Explanation
The correct approach is for the Development Team to ensure that every Increment meets non-functional requirements, as these are critical for the overall quality and performance of the software. The other options suggest that responsibility lies elsewhere or that these requirements can be deferred, which could lead to issues in the final product.