Professional Scrum Master I (PSM I) — Question 163
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items `Done` by the end of the Sprint. Which three phrases best describe the purpose of a definition of `Done`? (Choose three.)
Answer options
- A. It controls whether the developers have performed their tasks.
- B. It provides a template for elements that need to be included in the technical documentation.
- C. It creates transparency over the work inspected at the Sprint Review.
- D. It trucks the percent completeness of a Product Backlog item.
- E. It guides the Development Team is creating a forecast at the Sprint Planning.
- F. It defines what it takes for an Increment to be ready for release.
Correct answer: C, E, F
Explanation
The correct answers, C, E, and F, highlight the importance of a definition of 'Done' in promoting transparency, guiding planning, and defining release readiness. Options A and D focus on task completion and tracking percentages, which do not capture the broader purpose of ensuring quality and readiness for release.