Professional Scrum Master I (PSM I) — Question 162
When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Answer options
- A. The Development Team.
- B. The Product Owner and all stakeholders.
- C. The Product Owner and the Development Team.
- D. The Scrum Master, project manager and Development Team.
Correct answer: C
Explanation
The correct answer is C because the Product Owner and the Development Team must collaborate to reassess the Sprint work, ensuring that priorities align with the project goals. Options A and B do not involve both key roles necessary for making informed adjustments, while D includes unnecessary roles that do not directly contribute to the Sprint's review process.