Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the Scrum Master? (Choose two.)

Answer options

Correct answer: B, E

Explanation

Options B and E are correct because they both promote proactive communication and collaboration within the team to address quality concerns. Option A is not effective as waiting until the Sprint Retrospective delays addressing the issue, while Option C focuses on testers rather than involving the Product Owner, and Option D incorrectly shifts responsibility solely to the Developers.