Professional Scrum Master I (PSM I) — Question 118
The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.
Answer options
- A. True
- B. False
Correct answer: A
Explanation
The correct answer is True because during Sprint Planning, the team defines the Sprint Goal, which outlines the purpose of the Sprint, along with creating the Sprint Backlog, which consists of the items to be completed. The other option, False, is incorrect as it contradicts the established Scrum framework.