Professional Scrum Master I (PSM I) — Question 117
Who can abnormally terminate a Sprint?
Answer options
- A. The Scrum Master
- B. The Development Team or its members.
- C. The Product Owner
- D. The Stakeholders
Correct answer: C
Explanation
The correct answer is C, the Product Owner, as they have the responsibility to manage the product backlog and determine the priority of work. While the Scrum Master facilitates the process, and the Development Team and stakeholders offer input, only the Product Owner has the authority to decide when to stop a Sprint due to changes in business priorities.