Professional Scrum Master I (PSM I) — Question 119
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
Answer options
- A. Identifying high priority process improvements for the next Sprint.
- B. The order of items in the Product Backlog.
- C. How the team collaborates.
- D. Documenting acceptance criteria for items in the next Sprint.
Correct answer: A, C
Explanation
Options A and C are correct because a Sprint Retrospective focuses on improving team processes and collaboration. Option B is incorrect as it pertains to backlog management, which is not the primary focus of a retrospective. Option D is not suitable because documenting acceptance criteria is typically done during the Sprint Planning rather than the retrospective.