Professional Scrum Master I (PSM I) — Question 11
Multiple Scrum Teams working on the same project must have the same Sprint start date.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is B because while multiple Scrum Teams can work on the same project, they do not need to synchronize their Sprint start dates. This allows teams to operate independently and adapt their Sprints based on their specific needs, unlike option A, which incorrectly assumes uniformity in Sprint schedules.