Professional Scrum Master I (PSM I) — Question 10
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer options
- A. The Sprint Backlog.
- B. The Sprint Goal
- C. The release plan.
- D. Sprint Review minutes.
Correct answer: B
Explanation
The Sprint Goal is essential as it provides the Development Team with a clear focus and direction for their work during the Sprint. The Sprint Backlog contains the tasks to be completed, the release plan outlines future releases, and Sprint Review minutes summarize the review but do not offer specific guidance for the current Sprint.