Professional Scrum Master I (PSM I) — Question 12

How much time is required after a Sprint to prepare for the next Sprint?

Answer options

Correct answer: D

Explanation

The correct answer is D because in Scrum, a new Sprint commences right after the conclusion of the previous one without any scheduled breaks. Options A, B, C, and E suggest various breaks or preparatory times, which are not in line with the Scrum framework that emphasizes continuous delivery.