Professional Scrum Master I (PSM I) Free Practice Exam Questions

181 real Professional Scrum Master I (PSM I) exam questions with answers and AI explanations. Scrum.org certification prep — page 2 of 19.

  1. Question 11: Multiple Scrum Teams working on the same project must have the same Sprint start date.
  2. Question 12: How much time is required after a Sprint to prepare for the next Sprint?
  3. Question 13: What is a Development Team responsible for? (Choose two.)
  4. Question 14: A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which thre…
  5. Question 15: How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
  6. Question 16: What are three ways Scrum promotes self-organization? (Choose three.)
  7. Question 17: The CEO asks the Development Team to add a `very important` item to a Sprint that is in progress. What should the Development Team do?
  8. Question 18: The length of a Sprint should be:
  9. Question 19: Which three behaviors demonstrate that a team is self-organizing? (Choose three.)
  10. Question 20: At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their need…