SAP Certified Associate – SAP S/4HANA Production Planning and Manufacturing (2023) — Question 2
How can you set up the supply source for the Kanban process in SAP S/4HANA Cloud Private Edition? (Choose three.)
Answer options
- A. Use purchase orders for external procurement.
- B. Use stock transfer reservations for stock transfer.
- C. Use quotations for internal and external procurement.
- D. Use run schedule quantities for in-house production.
- E. Use purchasing costs for automated source prioritization.
Correct answer: A, B, D
Explanation
The correct answers A, B, and D focus on specific procurement and production methods relevant to the Kanban process. Option C is incorrect because quotations are not a method for establishing supply sources in this context, and option E does not directly pertain to configuring the supply source within the Kanban framework.