SAP Certified Associate – SAP S/4HANA Production Planning and Manufacturing (2023) — Question 3

Your production planners are allowed to execute planning only for specific resources.
How can you achieve this in Advanced Planning (PP/DS)?

Answer options

Correct answer: C

Explanation

The correct answer is C, as a planning group allows you to define specific resources for which planners can execute planning. Options A, B, and D do not provide the necessary restrictions on resource planning access for the production planners.