SAP Certified Associate – SAP S/4HANA Production Planning and Manufacturing (2023) — Question 1
How would you define pegging in the context of Advanced Planning?
Answer options
- A. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements and stock
- B. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements
- C. An evaluation to identify overstock situations in the balance between the receipt and the issue elements after the production planning run
- D. An evaluation to identify material or capacity shortages in the bill-of-material structure after the production planning run
Correct answer: B
Explanation
The correct answer is B because pegging specifically refers to the evaluation based on the bill-of-material structure that connects receipt and issue elements. Options A, C, and D describe evaluations based on different contexts without the specific focus on the bill-of-material structure, making them incorrect in the context of pegging.