PRINCE2 Practitioner 6th Edition — Question 8

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.
Is this an appropriate action, and why?

Answer options

Correct answer: D

Explanation

Option D is correct because discussing the team plan with the supplier can provide clarity on the timeline and ensure that all parties are aligned. Options A and B are incorrect as they do not address the root cause of the delay, and Option C is also wrong since the project manager’s immediate concern should be to confirm the supplier's schedule rather than check interfaces.