PRINCE2 Practitioner 6th Edition — Question 9

During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages.
Is this appropriate for a risk register, and why?

Answer options

Correct answer: A

Explanation

The correct answer is A because project registers need to be tailored to the specific needs of the organization to be effective. Option B, while valid, does not directly justify the use of an integrated register. Options C and D are incorrect as they focus on additional components that are not essential for the risk register's effectiveness.