PRINCE2 Practitioner 6th Edition — Question 7

MANAGING A STAGE BOUNDARY -
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?

Answer options

Correct answer: B

Explanation

The correct answer is B because updating the business case requires a revision of the overall plan and resources based on the actual performance from stage 3. Option A focuses on dependencies, which is not directly related to updating the business case. Option C is about supplier performance, and option D deals with future planning rather than current business case updates.