PRINCE2 Practitioner 6th Edition — Question 7
MANAGING A STAGE BOUNDARY -
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?
Answer options
- A. Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.
- B. Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.
- C. Review the performance of the external suppliers who worked on delivery of the 'e-learning course' during stage 3.
- D. Re-plan when the number of learners using the pilot course, and their increased knowledge, will be measured during stage 4.
Correct answer: B
Explanation
The correct answer is B because updating the business case requires a revision of the overall plan and resources based on the actual performance from stage 3. Option A focuses on dependencies, which is not directly related to updating the business case. Option C is about supplier performance, and option D deals with future planning rather than current business case updates.