PRINCE2 Practitioner 6th Edition — Question 6

The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for stage 3.
Is this appropriate as part of the 'directing a project' process, and why?

Answer options

Correct answer: D

Explanation

The correct answer is D because the project board should ensure that all product descriptions are thoroughly evaluated before they approve the stage plan. Options A and B incorrectly focus on project assurance's role rather than the board's responsibility, while option C misplaces the accountability for product descriptions.