PRINCE2 Practitioner 6th Edition — Question 5

During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.
Is this an appropriate way to carry out the 'plan the initiation stage' activity, and why?

Answer options

Correct answer: C

Explanation

The correct answer is C because the initiation stage focuses on establishing the project framework rather than planning subsequent stages. Options A and B incorrectly suggest that the initiation work can be planned in the same way as later phases, while D misplaces the responsibility of assessing project viability, which is primarily the project manager's role.