PRINCE2 Foundation — Question 96
Which is an objective of the Starting up a Project process?
Answer options
- A. Identify who will be responsible for creating the Project Plan
- B. Agree how the project will be monitored and controlled after initiation
- C. Authorize the Project Manager to proceed with the initiation stage
- D. Agree how issues and changes will be identified, assessed and controlled
Correct answer: A
Explanation
The correct answer is A, as the Starting up a Project process focuses on identifying the individual responsible for creating the Project Plan. Options B, C, and D pertain to later stages of project governance and management rather than the early planning phase.