PRINCE2 Foundation — Question 97
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
Answer options
- A. Product Description
- B. Team Plan
- C. Work Package
- D. Stage Plan
Correct answer: C
Explanation
The correct answer is C, 'Work Package', as it is specifically designed to outline the scope, time, and cost tolerances for a Team Manager's work. The other options, while related to project management, do not serve the same purpose in defining tolerances for specific tasks.