PRINCE2 Foundation — Question 95

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Answer options

Correct answer: C

Explanation

The correct answer is C, as 'Controlling a Stage' is specifically designed to monitor and manage the delivery of products within a stage, ensuring that any changes are controlled. The other options, while related to project management, do not focus specifically on controlling changes during a stage's delivery.