PRINCE2 Foundation — Question 8
Which level of management sets the project level tolerances?
Answer options
- A. Project board
- B. Team manager
- C. Corporate, programme management or the customer
- D. Project manager
Correct answer: C
Explanation
The correct answer is C, as it is the corporate, programme management, or the customer that defines the tolerances that guide project execution. The project manager (D) and team manager (B) operate within these tolerances, while the project board (A) oversees the project but does not set these specific tolerances.