PRINCE2 Foundation — Question 7
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Answer options
- A. Project mandate
- B. Initiation stage plan
- C. Project initiation documentation
- D. Project brief
Correct answer: D
Explanation
The Project brief is the correct answer because it is specifically designed to define and confirm the scope of the project during the initial phase. The other options, while relevant to project initiation, do not serve the primary purpose of outlining and validating the project's scope in the same way as the Project brief.