PRINCE2 Foundation — Question 9

Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty

Answer options

Correct answer: A

Explanation

The correct answer is A, as the quality theme focuses on implementing continuous improvement and ensuring stakeholder acceptance of the project's products. Options B and C include objectives that relate more to project viability rather than quality, while option D includes control of uncertainty, which is not a primary purpose of the quality theme.