PRINCE2 Foundation — Question 58
Which is a minimum requirement for applying the change theme?
Answer options
- A. To establish a change budget to fund changes in scope
- B. To appoint the project manager as part of the change authority
- C. To define the project's approach to baselining products
- D. To record every issue that is raised in the issue register
Correct answer: C
Explanation
The correct answer is C because defining the project's approach to baselining products is crucial for managing changes effectively. Options A, B, and D, while important for project management, are not minimum requirements specifically tied to the change theme.