PRINCE2 Foundation — Question 58

Which is a minimum requirement for applying the change theme?

Answer options

Correct answer: C

Explanation

The correct answer is C because defining the project's approach to baselining products is crucial for managing changes effectively. Options A, B, and D, while important for project management, are not minimum requirements specifically tied to the change theme.