PRINCE2 Foundation — Question 59
Which activity takes place within the Managing a Stage Boundary process?
Answer options
- A. Produce Highlight Reports
- B. Take corrective action within the limits of a stage's tolerance
- C. Produce an Exception Plan
- D. Authorize a Stage Plan for the next stage
Correct answer: C
Explanation
The correct answer is C, as the Managing a Stage Boundary process involves producing an Exception Plan when the stage is not meeting its objectives. Options A and B are related to monitoring and managing the current stage, while option D pertains to planning for the next stage, which occurs after the Managing a Stage Boundary process.