PRINCE2 Foundation — Question 57
Which is created during the Starting up a Project process?
Answer options
- A. Project mandate
- B. Project management team role descriptions
- C. Communication Management Strategy
- D. Quality Register
Correct answer: B
Explanation
The correct answer is B, as the Starting up a Project process involves defining the roles and responsibilities of the project management team. Options A, C, and D do not pertain to this specific phase and are created at different stages of project management.