PRINCE2 Foundation — Question 56

Which principle helps to ensure that all changes to the outputs are agreed?

Answer options

Correct answer: B

Explanation

The correct answer, 'Focus on products', emphasizes the importance of aligning changes with stakeholder agreements regarding outputs. The other options, while important for project management, do not specifically address the need for agreement on changes to outputs.