PRINCE2 Foundation — Question 55
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
Answer options
- A. At the start of the project
- B. Throughout each stage
- C. When a change is raised
- D. In exception situations
Correct answer: B
Explanation
The correct answer is B because the business justification needs to be continuously reviewed throughout each stage to ensure the project remains viable and aligned with its objectives. Options A, C, and D do not provide the ongoing assessment required, as they suggest limited or infrequent reviews.