PRINCE2 Foundation — Question 334
Which is a PRINCE2 time-driven control?
Answer options
- A. End stage report
- B. Project brief
- C. Project initiation documentation
- D. Checkpoint report
Correct answer: D
Explanation
The Checkpoint report serves as a time-driven control in PRINCE2, providing regular updates on project progress. The other options, such as the End stage report, Project brief, and Project initiation documentation, serve different purposes and are not specifically time-driven controls.