PRINCE2 Foundation — Question 333
Which is a minimum requirement for applying the 'organization' theme?
Answer options
- A. To provide unified direction to the project through a democratic project board
- B. To delegate responsibility for managing product delivery to team managers
- C. To allocate a separate group to carry out project support tasks
- D. To document the rules for delegating change authority responsibilities, if required
Correct answer: D
Explanation
The correct answer is D because documenting the rules for delegating change authority is essential to clarify responsibilities and ensure proper governance within the project. Options A, B, and C, while relevant to project management, do not address the specific requirements related to the organization theme as directly as option D does.