PRINCE2 Foundation — Question 335
What must be recorded in the quality management approach to meet the minimum requirements for managing quality?
Answer options
- A. The quality management activities planned to take place throughout the project's life
- B. The explicit quality criteria for each of the products to be created by the project
- C. The way the project will use product-based planning to plan quality activities
- D. The way that quality management will be communicated throughout the project's life
Correct answer: A
Explanation
The correct answer is A because it emphasizes the need to outline the planned quality management activities for the entire project duration, which is essential for effective quality control. Options B, C, and D, while important, do not directly address the minimum requirements for documenting quality management activities.