PRINCE2 Foundation — Question 327
Which is a benefit of using PRINCE2?
Answer options
- A. It replaces the need to apply specialist and industry-specific lifecycle models
- B. It ensures stakeholders are represented appropriately in project decision-making
- C. It requires no tailoring when being implemented in large corporate projects
- D. It ensures that the project team regards on-time delivery as the main objective
Correct answer: B
Explanation
The correct answer, B, highlights the importance of stakeholder involvement in project decisions, which is a key tenet of PRINCE2. Option A is incorrect because PRINCE2 can complement other models rather than replace them. Option C is wrong as PRINCE2 often requires tailoring to fit specific project needs, especially in larger organizations. Option D is misleading, as PRINCE2 emphasizes delivering projects on time but does not prioritize it above other objectives.