PRINCE2 Foundation — Question 326

Which role is responsible for appointing the senior user in a project?

Answer options

Correct answer: B

Explanation

The executive is responsible for appointing the senior user, as they have the authority to make decisions regarding project stakeholders. The project manager focuses on day-to-day project operations, corporate management may have broader organizational responsibilities, and project assurance ensures project compliance without directly appointing users.