PRINCE2 Foundation — Question 326
Which role is responsible for appointing the senior user in a project?
Answer options
- A. The project manager
- B. The executive
- C. Corporate management
- D. Project assurance
Correct answer: B
Explanation
The executive is responsible for appointing the senior user, as they have the authority to make decisions regarding project stakeholders. The project manager focuses on day-to-day project operations, corporate management may have broader organizational responsibilities, and project assurance ensures project compliance without directly appointing users.