PRINCE2 Foundation — Question 325
Which is part of quality control?
Answer options
- A. Document the project's acceptance criteria in the Project Product Description
- B. Define the quality responsibilities of those involved in the production of the products
- C. Produce quality records to show that the planned quality activities have been carried out
- D. Maintain the corporate organization's quality management system
Correct answer: C
Explanation
The correct answer, C, refers to the generation of quality records that confirm the completion of planned quality activities, which is essential for quality control. Options A and B focus on defining criteria and responsibilities rather than the execution of quality activities, while option D relates to maintaining a system rather than the actual quality control processes.