PRINCE2 Foundation — Question 325

Which is part of quality control?

Answer options

Correct answer: C

Explanation

The correct answer, C, refers to the generation of quality records that confirm the completion of planned quality activities, which is essential for quality control. Options A and B focus on defining criteria and responsibilities rather than the execution of quality activities, while option D relates to maintaining a system rather than the actual quality control processes.