PRINCE2 Foundation — Question 328

Which statement about the length of management stages in a project is CORRECT?

Answer options

Correct answer: C

Explanation

The correct answer is C, as higher levels of major risk typically lead to shorter stages to allow for quicker response and adaptation. Options A and B are incorrect because they suggest that higher risks require longer stages or that stage length depends on board availability, which is not true. Option D is also incorrect; while management stages help in control, their length is not strictly time-driven but rather influenced by risk levels.