PRINCE2 Foundation — Question 311

Which role is responsible for ensuring that the project management team works well with all the functional units involved in the project?

Answer options

Correct answer: B

Explanation

The Project Manager is tasked with overseeing the project's execution and ensuring effective communication and collaboration among all functional units. The Project Board provides overall direction, the Team Manager focuses on the specific team dynamics, and Project Assurance verifies that project processes are followed, but none are primarily responsible for the collaborative function like the Project Manager.