PRINCE2 Foundation — Question 310

Who represents the three project interests on a project?

Answer options

Correct answer: D

Explanation

The Project board is responsible for representing the three key project interests: business, user, and supplier. The Project manager focuses on executing the project, while Project support and External project stakeholders do not have the authority to represent these interests collectively.