PRINCE2 Foundation — Question 310
Who represents the three project interests on a project?
Answer options
- A. Project manager
- B. Project support
- C. External project stakeholders
- D. Project board
Correct answer: D
Explanation
The Project board is responsible for representing the three key project interests: business, user, and supplier. The Project manager focuses on executing the project, while Project support and External project stakeholders do not have the authority to represent these interests collectively.