PRINCE2 Foundation — Question 309
The project manager needs to report to the project board on the status of the project’s issues.
Which management product should the project manager review?
Answer options
- A. Project log
- B. Project brief
- C. Checkpoint report
- D. Highlight report
Correct answer: A
Explanation
The correct answer is A, the Project log, as it contains a record of all issues and their statuses, which is crucial for reporting to the project board. The Project brief (B) is used for initial project information, Checkpoint report (C) focuses on progress against plans, and Highlight report (D) summarizes key points but may not detail all issues.