PRINCE2 Foundation — Question 308

Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions

Answer options

Correct answer: C

Explanation

The correct answer is C because the 'managing a stage boundary' process focuses on providing insights about the current stage's performance and reviewing the project management team structure. Options A and D do not align with the core objectives of this process, while option B misses the aspect of team structure review.