PRINCE2 Foundation — Question 307
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
Answer options
- A. activities
- B. processes
- C. products
- D. quality
Correct answer: B
Explanation
The correct answer is 'processes' as PRINCE2 specifically includes processes as a key element for effective project management. The other options do not represent one of the four integrated elements defined by the PRINCE2 methodology.